Frequently Asked Questions

Back to top

Why was the Building & Construction Industry Payments Act created?

  • Over several years the Builidng Services Authority has actively campaigned for new payment legislation for the building and construction industry.
  • The Building and Construction Industry Payments Bill 2004 was introduced into Parliament on 18 March 2004.
  • Parliament debated and passed the Bill - 11May 2004.
  • An earlier version of the Bill was introduced into Parliament in November 2003 - lapsed due to the calling of State Election.

Back to top

Is there similar legislation in existence elsewhere in Australia?

  • Many of Australia's States and Territories have payment legislation in place.

Back to top

What are the objectives of the Act?

  • To ensure that a person is entitled to receive and recover progress payments for the carrying out of building & construction work or supplies related goods and services under a construction contract in Queensland
  • To provide a quicker and cost effective resolution of payment disputes than the court system

Back to top

How are these objectives achieved?

  • The Act creates a statutory right for persons to receive progress payments.
  • The Act creates a statutory right for persons to recover progress payments via:
    • The making of a payment claim by the person claiming payment;
    • The provision of a 'payment schedule' by the person who received the payment claim;
    • The referral by the person claiming payment of a disputed claim, or a claim that is not paid in full, to an Authorised Nominating Authority who appoints an adjudicator for a decision;
    • An "adjudicator" deciding a disputed progress payment

Back to top

What does the Act apply to?

  • With some exemptions, the Act applies to all "construction contracts" where a person:
    • "Carries out building & construction work"; or
    • "Supplies related goods or services" in Queensland.
  • Contracts also include ORAL contracts.
  • The types of contractual arrangements captured by the Act include:
    • Contractors against principals/developers;
    • Subcontractors against contractors;
    • Suppliers against subcontractors/contractors;
    • Plant and equipment hirers against subcontractors/contractors;
    • Consultants against clients;

Back to top

When can a person make a payment claim for the payment of a progress payment?

  • The Act provides a statutory right to make payment claims from:
    • Date calculated in accordance with contract (reference date);  or
    • the last day of each calendar month if no reference date provided in a contract.

Back to top

What should a payment claim state?

  • A "payment claim" should:
    • Be in writing and addressed to the person with whom you contracted (the Respondent)  (not superintendent);
    • Identify the construction work or related goods or services to which the claim relates;
    • State the amount of the claim;
    • State words to the effect of "This is a Payment Claim made under the Building and Construction Industry Payments Act 2004 (Qld).

Back to top

What must a Respondent do when they receive a 'payment claim'?

  • On receiving a payment claim under the Act the Respondent has 2 options:
    • Pay the claim in full on or before the due date; and/or 
    • Respond to the claim by serving a 'payment schedule'.
  • PRESCRIBED TIME - A payment schedule must be served within 10 business days, or such earlier time as stated in the contract.

Back to top

What should a 'payment schedule' state?

  • A 'payment schedule' should:
    • Identify the payment claim to which it relates;
    • Indicate the amount the Respondent proposes to pay;
    • If the amount is less than the amount claimed, specify the reasons why the amounts differ.

Back to top

What are the consequences of not providing a 'payment schedule'?

  • If the payment claim is valid, the full amount of the claim is deemed to be due and payable.
  • The Claimant can recover the unpaid portion of the claim as debt in summary  court proceedings.
  • In any summary court proceedings the Respondent cannot raise any cross claims in respect of the construction contract (i.e. that the work was not actually done or is defective).
  • The Claimant may suspend future work with 2 business days notice if the amount claimed is not paid by the due date.

Back to top

What are some other issues relating to the payment of claims?

  • A progress payment is payable on the submitting of a payment claim:
    • Subject to the contract not containing a 'void' provision, the time stated in the contract, referred to as the 'due date for payment'; or
    • If no time, or a void provision is stated in the contract, then due date for payment is within 10 business days of the payment claim being served.
  • If the amount stated in the payment schedule is not paid:
    • The Claimant can recover the unpaid portion of the claim as debt in summary proceedings.
    • In any summary proceedings the Respondent cannot raise any cross claims in respect of the construction contract (i.e. that the work was not actually done or is defective).
    • The Claimant may suspend performance of future work with 2 business days notice if the amount claimed is not paid.

Back to top

Are there any payment contractual provisions that are 'void'?

  • Provision for payment in a 'subcontract' between a builder and subcontractor later than 25 business days after submission of payment claim, is void.
  • Provision for payment in a 'commercial building contract' between a builder and a principal later than 15 business days after submission of payment claim, is void.
  • "Pay when paid" clauses are void.

Back to top

Does the Act provide a method for the valuing of payment claims?

  • The Act provides for a method of valuing payment claims if:
    • The written contract is silent on this issue; or
    • There is only an oral contract in place.

Back to top

What are the implications for persons (Claimants) lodging payment claims under the Act?

  • Claimants may seek payment of progress payments under the Act without the need to resort to costly and time-consuming legal processes.
  • Claims are for payment on account. It is still possible to take separate proceedings to prove a party's final entitlement to a payment claim.
  • All persons preserve their contractual rights.
  • Nothing under the Act affects any right that a party has under a construction contract.
  • Nothing under the Act affects any civil proceedings before a court or tribunal in relation to any matter arising under a construction contract.

Back to top

What are the implications for persons (Respondents) receiving payment claims under the Act?

  • Respondent needs to have good "contract administration" - review your current methods now.
  • Payment schedules must be issued in the correct form, within time, dot-pointing ALL the REASONS if there is a dispute with the amount mentioned in the payment claim

Back to top

When can a Claimant proceed to adjudication?

  • A Claimant may lodge an adjudication application where either:
    • The payment schedule is less than the payment claim;
    • No payment schedule is issued within the prescribed time;
    • The schedule amount is not paid, or only partly paid by the 'due date' for payment.

Back to top

How does the adjudication process work?

  • The Claimant lodges an Adjudication Application with an Authorised Nominating Authority ("ANA").
  • The Adjudication Application must be made within either:
    • 10 business days of receiving a payment schedule, where the payment schedule amount is less than the payment claim amount; or
    • 20 business days after the due date for payment, where the Respondent fails to pay the whole or any part of the scheduled amount, or
    • 15 business days of the Claimant serving a notice* on the Respondent, where the Respondent has:
      • NOT SERVED A PAYMENT SCHEDULE within the prescribed time; and
      • NOT PAID WHOLE OR ANY PART of the claimed amount by the due date for payment.

  • * This 'NOTICE of Intention to Apply for Adjudication" must be made within 20 business days immediately following 'due date' for payment.

Back to top

What should an adjudication application contain?

  • The Adjudication Application:
    • Must be in writing; and
    • Must identify the payment claim to which it relates; and
    • Must identify the payment schedule (if any) to which it relates; and
    • May contain any submissions the Claimant intends to rely upon.

Back to top

Where does a Claimant lodge an adjudication application?

  • An Adjudication Application can only be lodged with an Authorised Nominating Authority (ANA), not directly with an Adjudicator.
  • Refer to information  - About Authorised Nominating Authorities

Back to top

How is an adjudicator appointed to decide an adjudication application?

  • The ANA will nominate a registered Adjudicator to decide the Adjudication Application.

Back to top

Does the Respondent have an opportunity to provide a response to the adjudication application?

  • The Respondent may give the Adjudicator a 'response' to the Adjudication Application within -

    WHICHEVER IS THE LATER of:

    • 5 business days of receiving the copy of the Adjudication Application;

      OR

    • 2 business days after receiving notice of the Adjudicator's acceptance of the application.
  • The Respondent is only entitled to provide an adjudication response if the respondent has first served a payment schedule, within the allowed timeframe, on the claimant

Back to top

What should an adjudication response contain?

  • The response:
    • Must be in writing; and
    • Must identify the adjudication application to which it relates; and
    • May contain any submissions the Respondent intends to rely upon.

Back to top

Can an adjudication response raise any new issues which were not raised by the Respondent in their 'payment schedule'

  • The response:
    • CANNOT add any new reasons for dispute of the payment claim, that were not already identified in the payment schedule.
    • CAN expand upon the reasons already outlined in the payment schedule.

Back to top

How long does an adjudicator have in which to decide an adjudication application?

  • The Adjudicator must decide the adjudication application within 10 business days* after the earlier of the -
    • Date the Adjudicator receives the adjudication response; or
    • Date on which the Adjudicator should have received the adjudication response.
  • * UNLESS the Claimant and Respondent agree to extend the 10 day period.

Back to top

How does an adjudicator go about deciding an adjudication application?

  • The Adjudicator may:
    • Request further submissions from the parties
    • Call a conference (without legal representation)
    • Inspect the work

Back to top

What does an adjudication decision contain?

  • The Adjudicator:
    • Must give a written decision; and
    • Include the reasons for the decision
  • The Adjudicator is to decide the:
    • 'Adjudicated amount' of the progress payment, if any, to be paid by the Respondent to the Claimant; and
    • Date the 'adjudicated amount' becomes payable; and
    • Rate of interest payable.

Back to top

When should a Respondent pay any amount decided by an adjudicator to a Claimant?

  • The Respondent must pay any amount decided by the adjudicator, by the 'relevant date' which is prescribed as:
    • 5 business days of receiving the decision; or
    • If the Adjudicator decides a later date that the amount becomes payable, then that date.

Back to top

What happens if the Respondent does not pay the adjudicated amount?

  • If the Respondent fails to pay the whole or any part of the adjudicated amount by the 'relevant date', the Claimant may:
    • Ask the ANA to provide an 'Adjudication Certificate'; and/or
    • Suspend future work or the supply of goods or services, by service of a notice to do so.

Back to top

What is an 'Adjudication Certificate'?

  • An 'Adjudication Certificate' must state the:
    • Name of the Claimant;
    • Name of the Respondent;
    • 'Adjudicated amount';
    • Date on which payment of the adjudicated amount was required to be paid to the Claimant.

Back to top

What does an 'Adjudication Certificate' contain?

  • The 'adjudicated amount for an Adjudication Certificate' is comprised of:
    • The 'adjudicated amount' determined by the Adjudicator, and
    • May also include the addition of:
      • The amount of interest payable on the adjudicated amount; and
      • Reimbursement to the Claimant of the Respondent's share of the adjudication fees, if such fees were paid by the Claimant.

Back to top

What does a Claimant do with an 'Adjudication Certificate'?

  • An 'Adjudication Certificate' -
    • May be filed as judgment debt, so that payment can be enforced in a Court of competent jurisdiction.
    • Must be accompanied by an 'Affidavit' from the Claimant stating that the whole or part of the adjudicated amount has not been paid.

Back to top

What is the end effect of an 'Adjudication Certificate'?

  • The issuing of an adjudication certificate allows a Claimant the opportunity to convert an adjudication decision into a decision of a competent court of jurisdiction.

Back to top

Can a Respondent seek to have a judgment debt set aside?

  • Yes

Back to top

Are there any limitations imposed on a Respondent seeking to have a judgment debt set aside?

  • If the Respondent commences proceedings to have judgment set aside, the Respondent is not entitled to -
    • Bring any counterclaim against the Claimant; or
    • Raise any defence in relation to matters arising under the construction contract
    • Challenge the Adjudicator's decision.
  • The Respondent must also pay into Court as security the unpaid portion of the adjudicated amount.

Back to top

How are ANAs and adjudicators paid?

  • An ANA and an Adjudicator are entitled to be paid.
  • Adjudication operates on a 'user-pays' basis.
  • The Claimant and Respondent are 'jointly and severably liable' to meet such fees - each are liable to contribute to the payment in equal portions, or in the portions the Adjudicator decides.

Back to top

Can an adjudicator refuse to release their decision until paid?

  • The Adjudicator has a 'lien' entitlement to withhold releasing their adjudication decision until their adjudication fees are paid.
  • A Claimant may pay the Respondent's portion of the fees, to have decision released and have this amount added to adjudicated amount when obtaining an Adjudication Certificate.

Back to top

Can parties contract out of the Act?

  • Parties cannot 'contract out' of the Building and Construction Industry Payments Act 2004.
  • The Act makes void any contract provision that:
    • Is contrary to the Act; or
    • Purports to annul, exclude, modify, restrict or otherwise change a provision of the Act; or
    • May be construed as an attempt to deter a person from taking action under the Act.

Back to top

Who registers ANAs and Adjudicators?

  • The Act establishes an "Adjudication Registry" which will register Authorised Nominating Authorities (ANA) and Adjudicators.
  • Comprehensive registration criteria will need to be met in order to become registered.
  • Conditions of Registration will apply to ANA's and Adjudicators to maintain registration status.
  • A breach of a condition may result in an ANA or Adjudicator having their registration suspended or cancelled.

Back to top

Are adjudication decisions published?

  • Establishment of a 'Public Record' of adjudication decisions and other information are to be maintained by the Adjudication Registry.

Back to top

 